Day 139

12-07-2018Church Renovation

The tile is almost done on the sanctuary. The carpeting on the stairs is almost done. The smaller side is already and it looks so nice. The lift part of the elevator was installed. The bathrooms are working with running water and a beautiful door. The stenciling is all complete with the final shell being painted under the choir loft. The Baptismal font will be placed directly underneath it. We have beautiful new lights hanging through out the church. The railing outside has been installed. The pews are getting installed but no picture. You will just have to wait on that view until the 16th. Everything is coming together. Do not forget that tomorrow is a Holy Day of Obligation in honor of our Church's namesake. Also, keep selling your raffle tickets! Have a great weekend!

Day 137

12-05-2018Church Renovation

The carpeting is looking good. She is working on laying carpet in the back of church going out to the landing. Sims Sounds is installing some of the sound system. The fans are installed in the confessionals. They are prepping the floor in Hansen Hall getting it ready for the carpet. We have doors on the bathrooms. They will be ready for Dec 16th.

Day 135

12-03-2018Church Renovation

The tile is getting installed and grouted in the sanctuary. They are almost done carpeting with one side of the church. Charlie is woodgraining the door and entrance into Hansen Hall.